Affordable housing on the Silver Spring United Methodist Church campus is one step closer to being a reality. With our development partners Enterprise Community Development and NFP Affordable Housing, we are pleased to announce that our Preliminary Plan for development and Conditional Use Plan will soon be formally considered by Montgomery County officials. Official documents associated with the proposed development can be found on the county’s Development Activity Information Center.
Both of these plans will be reviewed by the Montgomery Planning Board; the Conditional Use will be decided by the Montgomery County Office of Zoning and Administrative Hearings. Both entities will hold public hearings on the plans. Letters will soon be sent to Woodside, surrounding communities, and other interested parties with more information on hearings. See the updated timeline below.
HOUSING PROJECT TIMELINE
These are some of the major steps that must be undertaken leading up to the start of housing construction, with approximate timeframes for completion:
- December 15, 2026 – Montgomery Planning’s Development Review Committee discusses the application with the applicant in a meeting that is open to the public. No testimony will be presented at this meeting.
- March 18, 2027 – The Montgomery Planning Board holds a hearing on the Preliminary Plan application. Any approval would be held pending the outcome of the Conditional Use decision.
- Late March/April 2027 – A county hearing examiner will conduct one or more public hearings as needed to determine whether the project satisfies the requirements for a Conditional Use under the FAITH Zoning Text Amendment. The examiner may require changes to the architectural plans.
- Summer 2027 – Following the Conditional Use decision, the decision of the Montgomery Planning Board on the Preliminary Plan is finalized, and a final plat is approved.
- Fall 2027 thru Spring 2028 – The development team finalizes all plans for development of the site and for financing of the housing project and submits applications for permits.
- Spring/Summer 2028 – Construction starts.
Sign up for BBCC email notifications for the latest news on the SSUMC affordable housing project.